Replacement ABP Incineration Plant

We are in the process of finalising design details for a replacement of our existing animal by-products (ABP) incinerator at our Cambridge site. We have planning consent for the incinerator and intend to procure a facility with a capacity to incinerate up to 500kg per hour of ABP.

The incinerator will be equipped with state of the art features including:

  • 1600°C grade hot face refractory lining
  • Calcium silicate insulation
  • Temperature controlled burners
  • Hydraulically operated hearths in cascade
  • Forced combustion air
  • Excellent fuel efficiency

It is expected the facility will be operational in late 2017.

 

Customers

The Campus has been using Novus Environmental for nearly 20 years now. The quantity of waste that we now dispose of has more than doubled in those years. We have always found them to both competitive and cooperative.The service is just as good now as it was then.